Story summary Coordination
Iteration ItEr65week49To50
FEA ItEr65S01Coordination
Story Lead  
Next Story  
Passed acceptance test No

Acceptance Criteria

Additional Specification Comments

Implementation Notes

Time devoted to open the iteration and plan it.

-- JavierMoran - 09 Dec 2010

 

Delay Causes

Final or Pending Considerations

 

Entregables de código

%RPSHOWGITCOMMITS%

Tasks in this story

Tasks Est Spent To do Risk Reviewer Developer Task Name Start Date Est End Date End Date
Task 15 1.75 0 Low JavierMoran JavierMoran Coordination      

Total Hours in this Story

User Spent in XpTracker Spent in phpReport Ok?
JavierMoran 1.75 0 ALERT!
Total 1.75 0 ALERT!