  • 1.0 RC: freeze admitted contracts, package/dependency identities and supported Native/Lit matrix; at least fourteen days of real-product soak, install/upgrade/security, triage and human GO. Architecture changes return to Alpha; release fixes produce new qualified artifacts.

    No due date
    0/5 issues closed
  • Public 1.0 Alpha: application-driven API/architecture iteration; immutable qualification rounds, independent consumers, Native/Lit capability/runtime evidence, measured performance and fork maintenance. RC admission #1243 follows real application #1179; no circular RC dependency.

    No due date
    0/13 issues closed
  • Beta.2.1 Router/core; Beta.2.2 Framework/Document; Beta.2.3 cleanup closure and 1.0 Alpha admission. Three-working-day target from implementation start, no deadline waiver.

    No due date
    20/44 issues closed
  • No due date
    9/9 issues closed
  • Historical compiled train and current Beta.2.x convergence. ADR-0152 replaces the old Beta.3 successor with public 1.0 Alpha; stable 0.43 fallback unchanged.

    No due date
    31/32 issues closed
  • Stable release: API frozen, migration guide, all gates green, 7 days without P0 after RC.

    Overdue by 26 day(s)
    Due by August 14, 2026
    0/1 issues closed