2024 May 16

rrivera747 edited this page May 16, 2024 · 1 revision

Agenda:

  1. General TDAQ Project status updates/Schedule review.
  2. Status of DAQ room and AL9 transition, EPICS, Optical fiber plant, Test stands (IERC), and Server purchase.
  3. AOB

Eric -- Helping setup calorimter Sidet network. Has a setup for temperature scripts. AL9 move of IERC (last week of May in low pace, so we should avoid). Ryan will check with Pasha to decide on week.

Ryan -- CFO and DTC in daq room could not repeat Tracker VST connection issue. Likely RTF was not setup for daq22. CFO firmware adding CFO Event Record, adding DTC counters - prep for Global Run 2.

Javier -- With Mike Utes, trying to measure “max” node power at IERC. After swapping fibers and DTC cards, had trouble locking all fibers (combo of daq14 and daq07). Brought in Joe. Will want to try permutations of connections to understand power usage.

Glenn -- Merrill installed alarm system in the daq room. Focus is on CRV FEB.

Ralf -- 34KB/”onspill” ubunch “event” for full CRV zero-suppressed. Timeouts seem resolved. Added histograms.

Simon -- Two types of timeouts. The driver lock was not successful but was returning without exception. Flow should be to hold dcs lock until dcs exchange is complete. It might be worth claiming the g-2 GPS system.

Antonio -- Implemented new production db schema in ots. Looked at dcs-0 leaving connection open. Possibly from Ray or Simon?

Greg -- Need trigger evaluation of 22x g-2 nodes (from 2014). There is a risk on project for full node purchase.