# IBC - April 2025 Progress Update
2+
3+
## Intro
4+
This progress report is for IBC Integration related development work by iBriz Team.
5+
The next phase of the project will Intent and Solver development with Relay V3. The report is from 1-April-2025 to 30-April-2025
6+
7+
## Summary
8+
For more details please see : <br>
9+
https://github.com/icon-project/IBC-Integration <br>
10+
https://github.com/icon-project/ibc-relay <br>
11+
https://github.com/icon-project/xcall-multi <br>
12+
https://github.com/icon-project/centralised-relay<br>
13+
https://github.com/icon-project/intent-relay<br>
14+
https://github.com/icon-project/Icon-network-solver<br>
15+
https://github.com/icon-project/intent-contracts
16+
17+
## Milestones
18+
Milestone 1 - Testnet Deployment on Archway and ICON - 11th August 2023 - Completed <br>
19+
Milestone 2 - Testnet Deployment - ICON - Libson, Archway and Neutron - 12th September 2023 - Completed <br>
20+
Milestone 3 - Mainnet Deployment - ICON and Archway - 6th October 2023- Completed <br>
21+
Milestone 4 - Mainnet Deployment - IBC Neutron - 31st October 2023- Completed <br>
22+
Milestone 5 - Mainnet Deployment - IBC Injective - 5th January 2024 - Completed <br>
23+
Milestone 6 - Centralised Relay for Avalanche and ICON - 19th January 2024 - Completed <br>
24+
Milestone 7 - xCall deployments for Wormhole and LayerZero - 5th February - Completed <br>
25+
Milestone 8 - Centralised Relay integration for Archway - 29th March - Completed <br>
26+
Milestone 9 - Hopchain and ICS20 Integration to IBC - TBD - In Progress <br>
27+
Milestone 10 - xCall on SUI - August 2024 - Completed <br>
28+
Milestone 11 - xCall on Neon EVM - TBD - On Hold <br>
29+
Milestone 12 - xCall on Stellar - September 2024 - Completed <br>
30+
Milestone 13 - xCall on Solana - September 2024 - Completed <br>
31+
Milestone 14 - Swap Intent - December 2024 - In Progress <br>
32+
Milestone 15 - Relay Cluster - December 2024 - Completed <br>
33+
34+
35+
## Deliverables Ready
36+
37+
| Name | Development State | Notes | Source / location |
38+
|:----- |:------------------ | :----| :----------------|
39+
| Relay Cluster | Completed | Centralized Relay V2 - Mainnet Deployments. Only SUI remaining to migrate to cluster | https://github.com/icon-project/ibc-planning/issues/495 |
40+
| Asset Managers | Completed | Deployed on Mainnet | https://github.com/orgs/icon-project/projects/12/views/2?sliceBy%5Bvalue%5D=Asset+managers |
41+
| Solver SDK SUI | In Progress | New world integration in progress | https://github.com/icon-project/operation-liquidity-layer/issues/173 |
42+
| Solver SDK Stellar | In Progress | New world integration in progress | https://github.com/icon-project/operation-liquidity-layer/issues/174 |
43+
| Solver SDK ICON | In Progress | New world integration in progress | https://github.com/icon-project/operation-liquidity-layer/issues/195 |
44+
| Solver: Stellar New World| In Progress | New world integration in progress | https://github.com/icon-project/Icon-network-solver/issues/152 |
45+
| Solver: Solana New World| In Progress | New world integration in progress | https://github.com/icon-project/Icon-network-solver/issues/151 |
46+
47+
48+
## Deliverables Projected for Next Cycle
49+
50+
51+
| Name | Development State | Notes |
52+
|:-----|:------------------|:------|
53+
| Spoke Cross Chain Token | Deployment and Testing | https://github.com/icon-project/operation-liquidity-layer/issues/175 |
54+
| Relay V3 | Deployment | Continue deployment on non EVM chains - https://github.com/icon-project/intent-relay/issues/1 |
55+
| Asset Managers | Audit and Deployment | Audit Fix and Mainnet Deployment for Solana and Stellar https://github.com/orgs/icon-project/projects/12/views/2?sliceBy%5Bvalue%5D=Asset+managers |
56+
57+
58+
## Sample of docs
59+
https://github.com/icon-project/IBC-Integration <br>
60+
https://github.com/icon-project/ibc-relay <br>
61+
https://github.com/icon-project/xcall-multi <br>
62+
https://github.com/icon-project/centralised-relay